Siding, Shake, Insulation, Drywall, and Brick/Stone - all in two weeks!!!!


Oct 15 - The facia and the vinyl shake in the gables gets installed.  Looks pretty nice with that roof...let's see how the rest of it will look.


The siding is going along really well and fast.  These guys don't mess around.  We picked Irish Thistle for the siding color with is a really cool bluish green color.  I think it looks amazing as it contrasts the dark bronze window trim color.


The white garage door and outlets look a little funny now but they will be painted later on.


Getting the forms set up to pour the back patio.


Oct 18 - Insulation crew has been through and got most of the exterior walls of the house.  We upgraded to the 2x6 walls to keep this house as warm as possible with the extra insulation...so worth it because with no heat on and just the insulation up right now, it's not too bad in here.



Oct 19 - Insulation put up on the walls between the main house and the garage walls.


Oct 20 - The drywall crew has started and they don't mess around either.  We tried peaking in but it sounded like there was an orchestra of drills going on a rampage inside so we stayed out.  But at night Kevin walked around and saw all the extension cords piled up and knew that some serious drywall screwing was going on.


Drywall on the archway between kitchen and living room


Drywall in the hallway down towards the kids' room.


The pile of drywall scraps...Kevin said it was a disaster zone down at the house....



Oct 21 - Dry wall is done and the mess is cleared up.  Now our rooms are starting to take shape.  This is my kitchen with a walk in pantry.


The dining room - you can see the framing set up for the coffered ceiling.


This is standing in the living room looking back towards the open stairway to the basement.



Oct. 24 - The guys blowing the insulation in the attic were here today and let Harry hop up in the truck.

They also started forming up the driveway today.  Supposed to be getting weather in the 60's so they've moved up the pouring of the driveway a couple of weeks.


Looks like they got the garage mudded and taped.  



Later in the day they got the first section of the driveway poured.


October 25 - Got the second section of the driveway poured...wow...this is a big drive way.  So excited for the kids to be able to ride their bikes around on it.




October 31 - They started putting the brick and stone up today.  We've picked a stone mix called Wildwood Blend....it's got 4 different types of stones in it and lots of fun colors, but we've got that bit of English stone look in our house!!!