Thursday, August 25 - Basement floor poured and cut. Garage floor prepped and ready to pour.
Wednesday, August 31 - Garage floor poured
(looking at the back side of garage floor. We have an three car garage but it is double deep behind the 3rd and 1/2 of the 2nd stall so that we can have space for our outdoor stuff and a little workshop and gardening bench for me and Kevin.)
Friday, September 2 - Floor trusses secured to steel beams and sheeting soon ready to be installed next week.
(Our first chance to stand in our basement)
(Kevin and Harrison standing by the stairwell coming down from upstairs. It will come down halfway on the left side, then come to a landing, then curve down on the right side. We will have an open hand rail around the perimeter of it upstairs)
(this is looking down the long part of the basement which we'll used for a rec room and play area - at the end by the window will be a guest bedroom some day - I hope to have French doors opening into it so that we can let the light from the window shine through when we want it, but closed when guests need privacy)