Friday, July 26 - Temporary has been set up and house outline staked out.


(standing in front of my front door and porch)
Sunday, July 31 - Big digging machine on the lot and the water pipes hooked up.

Monday, August 1 - Hole for basement is dug!!!

Tuesday, August 2 - Footings poured for walls and supporting poles for beams.

Tuesday, August 2 (evening) - forms for exterior walls dropped off at lot.
Thursday, August 4 - Forms set up for basement walls to be poured
Friday, August 5 - Walls poured and forms pulled off.
(view from the road at our driveway and front of house)
(Addison thinks this looks pretty messy, but cool)

(The kids' favorite thing to do this week is play in the big dirt pile behind the house)